Hoofers Health Club

View Gallery Hoofers Logo image

Client: Mr Jez Kearney (Proprietor)

Hoofers Health Club, 308c Victoria Centre, Nottingham. NG13QN

Existing Building: Victoria Shopping Centre

Health & Safety: CDM

Case Study

Complete refurbished Studio 2 due to water damage

Works Carried Out

Complete strip out of Studio 2 and replace with new.

Demolition: Decommission all ceiling lighting & fire alarm. Take down 122m² of damaged suspended ceiling grid & ceiling tiles and remove from site. Carefully remove full length mirrors and remove from site. Remove 122m² of damaged timber flooring & sub-floor & remove from site.

Dry out Studio 2: Using 4 number dehumidifiers (emptied twice daily )

Ceiling: 122m² Suspend ceiling was installed using a 600mm x 600mm recessed tile, incorporating lighting, air-conditioning units, fire alarm and security alarm.

Internal Joinery: To Studio 2

Form new sub-floor as existing using 50mm x 50mm treated timbers 122m² @ 400mm centres.

122m² of red wood t & g 21mm x 100mm flooring secret nailed.

46lm of 100mm soft wood skirting’s to match existing.

New Internal door with vision panel.

Supply & fit mirrored wall to the rear wall of studio 2   14.5 metres long by 1.7 metres high.

Decoration: All wood work primed under coated & white glossed, all new plastered walls 2 coats of trade emulsion.

New red wood timber floor was sanded down to receive smooth finish and was given 3 coat of clear varnish to give the floor a quality finish.

Electrical: Decommission lighting and supply & fix new lighting to new suspended ceiling & renew electrical sockets.

Conclusion

This was a delicate project due to the nature of the building and its opening times to the public.

Monday – Friday 5.30am – 11pm
Saturday 6.00 am – 7pm
Sunday 9.00 am – 7pm

Studio 2 is located in the middle of Hoofers Gym and all waste and materials delivered to site had to be carried outside the hours above and the works had to be carried out when the in full use.

The total project was carried out from demolition to completion was 4 weeks.