Case Study

Single storey traditional brick extension, forming  2 class rooms, one to one room, staffroom,  kitchen and new toilet facilities. External ground works consisting of drainage, designed soak away and 68 linear metres of 1.2 metres of tarmac paths to the perimeter of the new extension.

Works Carried Out

When D.L.Rhodes & Son Ltd took over the works at Burton Joyce Primary School we given of a dead line for completion as the school in desperate need of the use of the  new class rooms  & staff room, as the previous construction company fallen into receivership and left the school with a unfinished building.

Works carried by D.L.Rhodes & Son Ltd

Floor Slab: Dpm, Insulation and lay 270m² of 50mm flow screed.

Insulation to Ceiling void: 270m² of 100mm kingspan cut & fitted between ceiling joists.

External PVC Windows: 5 Windows & 1 External Door .

Plasterboard & Skim: 490m² of plasterboard & skim using 12.5mm plaster board and dry wall adhesive finished with a plaster skim.

Mechanical & Electrical: Air-condition units were installed into the ceiling grid in extended room 1 and wall mounted in all others to give the school the advantage choosing between heating and cooling.

Electrical: Power sockets to all rooms, CAT 2 lighting including emergency lighting installed to the new ceiling grid and external lighting to perimeter path.

Fire Alarm: Existing school fire alarm extended into the new extension.

Security Alarm: Existing security alarm extended into the new extension.

Ceiling: 270m² Suspend ceiling was installed using a 600mm x 600mm recessed tile, incorporating lighting, air-conditioning units, fire alarm and security alarm.

Internal Joinery:To classrooms & corridor;

Oak veneered doors with vision panels & softwood frame including intermittent smoke seals, including all Ironmongery (kick, finger plates, locks and door closers) 150lm softwood skirting’s with matching architrave

Two number kitchens to Extended Room 1 & Staffroom and Toilet Cubicles to Extended Room 1.

Purpose made storage units with sink to Extended Class Room 2.

Floor Coverings: Non slip altro flooring to wet areas and carpet tile to Class rooms, Staffroom and Corridor 270m² in total.

Decoration: All wood work primed under coated & white glossed, all new plastered walls 2 coats of trade emulsion.

Conclusion

All the building works to this project was carried out in normal school hour and the school stayed fully operational and minimum disruption   while the works were being carried out. The project was completed on time in 12 weeks and completed for the price Tendered.

Head Teacher’s Comments:

“DL Rhodes builders took over the completion of our extension and have done a magnificent job for us! We now have a wonderful extended services room, classroom and staffroom. We found Nigel and Paul very easy to work with from beginning to end and the quality of their workmanship has been superb! The timeline presented to us at the start of the project was kept to and any issues along the way have been sorted quickly and efficiently. All the health and safety requirements were spot on and DL Rhodes’ workforce were professional and courteous at all times. I would   absolutely recommend DL Rhodes to any school considering building work!”